There will be days when Tasks cannot be scheduled because your company is closed for that day - eg a public holiday like Christmas day.
Within Empower these are called Company Vacations - essentially these are days that Tasks cannot be scheduled on.
There are three ways to set up Company Vacations.
- The first way is to set up a Company Vacation for a single day or small number of days. To do this - see Adding a Single Company Vacation.
- The second way to add Company Vacations is to add a number of days at the same time. To do this - see Adding Several Company Vacation Days.
- The third way is to automatically add Company Vacations for a year for your country. To do this see - Adding Auto Vacations.
Once Company Vacations have been added you should be able to see them when viewing the Schedule in
- View > Scheduling > Schedule or
- Employee Schedule or
- Process Schedule,
then the Company Vacation dates will be highlighted in Blue (see below as an example)
Similarly when viewing Jobs Due Each week, in Job > Jobs Due Each Week, they will also be highlighted in Blue (see below)
Similarly in the View > Scheduling > Capacity pages Company Vacations will also be visible (see highlighted below)
Similarly in the View > Scheduling > Gantt Chart page, Company Vacations will be shown in a light blue color (see circled below)