Sequencing

Employees may have a number of Tasks Assigned to them, that they cannot begin work on because some other work has yet to be completed.

As an example, when making a table the sequence of Tasks may be

  • Cut
  • Assemble
  • Paint.

Painting cannot be carried out until assemble is underway.

Assemble cannot be carried out until cut is underway.

Cut is a preceding task to assemble, and assemble is a preceding task to paint.

Assembly is a succeeding task to cut, and paint is a succeeding task to assemble.

Within Empower this is called a Sequence.

Empower uses Sequencing to allow for

  • Various ways to hide succeeding Tasks, and
  • To set up following Tasks for Scheduling Auto Move.

To set up a Sequence,

  1. From the Main Management Menu go to Product > Edit.

You should see a page similar to

Select a Product.

You should see a page similar to

  1. Click on the highlighted Sequence button.
  1. And select the preceding Process from the drop down box – in this case we will select Make Top.
  1. And click on Add and that’s it you have created a Sequence, from Make Top to Assembly.
  1. And click on Add and that’s it you have created a Sequence, from Make Top to Assembly.

Note that you can have more than one Preceding Process.

If you make a mistake just click on delete to delete that sequence.

Note that you cannot set up a Circular Sequence, or a complete loop. An example of a Circular sequence would be in the above example if the Sequence Cut à Assemble à Paint is added to by making Paint be a Preceding Process of Cut – i.e. the sequence loops around in a circle.

  1. To alter what Employees see in the Task Start Stop and Work Center pages in the Factory version, from the Main Management Menu go to Tools > Settings and select the General tab (highlighted below).

Under Show Sequenced Tasks (see highlighted above) are there are three options

  • Always show all Tasks - all Tasks will be visible. This is the default setting

  • Show Tasks where Task has started - all Tasks that have a preceding Process will be invisible until at least one Task in the Order has started

  • Show Tasks once Predecessor has started - Tasks that have a preceding Process will be invisible until the preceding one has started.